Repair the Kestrel Pass road this summer, because winter will charge us more

The Kestrel Pass closed for 41 days last winter at a cost of about M4.7 million. A M31 million repair would pay back in just over eight years on a road meant to last 30.

The Kestrel Pass road will close again this winter. That is not a forecast; it is a repair schedule that has been postponed three times. The only question left is whether we spend M31 million fixing it in the dry months, or spend about M4.7 million a year watching it fail.

Last winter the pass was shut for 41 days. Some of those closures were snow, which no engineer can prevent. But the transport ministry’s own log attributes 33 of the 41 days to drainage failure and rockfall on an 11-kilometre section between the Marrow Bay turn and the summit. Water gets behind the old retaining walls, freezes, and pushes them onto the carriageway. Crews clear the road, and the next thaw does it again.

Closures are easy to shrug at because their costs fall on other people. Add them up and they stop being small.

Freight comes first. About 1,900 trucks a month use the pass, or roughly 63 a day. When it shuts they take the lowland route by the Tamsin Canal road, a detour of 140 kilometres. At M2.10 a kilometre that is M294 a truck. Over 41 days, 2,583 truck journeys cost M759,000 extra.

Next, the mountain towns. Nadia Orsolo, the economist at Karsholm University, has surveyed shops, guesthouses and the sawmill at the summit and puts lost sales for the 41 days at M3.4 million.

Third, emergencies. The pass is the only road ambulance route between the upper valley and the hospital at Karsholm. Last winter 29 patients went by helicopter instead, at about M18,000 a flight, or M522,000.

Add the three: M0.76 million, M3.4 million and M0.52 million come to about M4.7 million a year. That figure leaves out the harder things to price, such as a missed dialysis appointment or a farm that sold its lambs a week late.

The ministry’s engineers have costed a full rebuild of the 11-kilometre section: new retaining walls, a drainage channel on the uphill side, and rock netting above the two worst slopes. The estimate is M31 million. Their model says closure days would fall from 41 to about 8, an 80 per cent reduction. Eighty per cent of M4.7 million is a saving of roughly M3.77 million a year.

Divide the cost by the saving and the payback is 8.2 years. The road is designed to last 30. Over that life the avoided costs come to about M113 million against an outlay of M31 million, before counting a single life or a single patient’s comfort.

“The pass has always closed in winter and the valley has always coped. Money spent here is money not spent on roads that carry ten times the traffic.” Extract from a ministry briefing note on capital priorities, quoted to the Transport Committee

The briefing note has a point about traffic. The pass carries fewer vehicles than the coast road, and a ministry with a fixed budget must rank its projects by return. I would not argue otherwise.

But it ranks the pass badly because it counts the wrong thing. Traffic volume measures how many people use a road; it says nothing about what happens to the people who lose it. The coast road has three alternatives. The pass has one, and that one is 140 kilometres long.

The note also assumes the savings arrive in full. Suppose they do not. If the repair delivers only half the benefit, the saving is M1.88 million a year and payback stretches to 16.5 years. That is still inside the road’s life. A project that earns its money back even when its sponsors are wrong by half is not a gamble.

Winter works on an alpine road cost roughly a third more than summer works, because crews lose daylight and concrete cannot be poured below freezing. The window for this year’s work is closing; the ministry should tender in January for a start in May. Every month of delay moves the first full season of the new road a year out.

The Assembly has talked about the pass for a decade. It should spend the M31 million, and then it can stop.